Click here to make tpub.com your Home Page

Page Title: HELICOPTER PREPARATION FOR USE AFTER C141B SHIPMENT.
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 

TM 55-1520-238-S
a. Remove
Shipping
Carrier
Tie
e. Unload Helicopter to Position Two. Re-
downs. Unfasten and remove four tie-
lease helicopter parking brakes. Have load-
down straps from each of two shipping car-
master slowly reelout cargo aircraft winch,
riers (eight tiedowns) (fig. FO2).
while kneeling or erecting helicopter (para-
graph 85 or 86) where required for over-
b. Remove Shipping Carriers. Remove
head and ramp hinge clearance. Carefully
shipping carrier wheel shoring.
guide helicopter down loading ramps until
230 HELICOPTER PREPARATION FOR USE
tail landing gear wheel is on the ground
(position two, fig. 229).
AFTER C141B SHIPMENT.
f. Reposition Auxiliary Ramp. Reposition
Preparation of the AH64A helicopter for use after
center auxiliary ramp to side of loading
C141B cargo aircraft shipment will be performed in
ramp so that ramp centerlines are 6 feet 8
accordance with instructions outlined in paragraphs
inches apart alined with main landing gear
230.1 through 230.23.
wheels and parallel to helicopter centerline.
230.1 Preliminary  Safety  Procedures. Before
g. Unload
Helicopter
to
Position
starting operations, perform safety procedures outlined
One. Have loadmaster slowly reelout
in paragraphs 230.2 and 230.3.
cargo aircraft winch, while kneeling or rais-
230.2 Ground Helicopters.
ing helicopter where required for overhead
TM 1-1520-238-23.
and ramp hinge clearance. Carefully guide
230.3 Perform
Helicopter
Safety
Check.
helicopter down loading ramps until main
TM 1-1520-238-23.
landing gear wheels are 61/2 feet aft of the
main ramp hinge (position one, fig. 229).
230.4 Unpacking and Depreservation.
h. Unload Helicopter to Ground Lev-
el. Reelout cargo aircraft winch and
230.5 Install Wings. Paragraph 216.6.
guide helicopter down ramps until main
230.6 Install Vertical Stabilizer. Figure 226 and
wheels are on the ground.
227.
i. Disconnect Cargo Aircraft Winch Cable
a. Disconnect Stabilator Actuator from
from Helicopter. Paragraph 228.9p.
Stowing Fixture. Remove clevis nut,
j. Erect Helicopter. Erect helicopter and
washers, and bolt from aft fixture actuator
disconnect hydraulic cart (paragraph 86).
link and actuator rod end eye. Retain rod
end hardware.
k. Unlock  Tail  Landing  Gear  Shock
b. Install
Stabilizer
Top
Sling
Straps. Preadjust sling straps (fig. 227).
l. Remove Tail Wheel Steering Bar and
Insert and lock two stabilizer sling short
Winching Yoke.  Paragraph 228.9o.
strap quickrelease pins in stabilizer top
229.21 Unload One M230 Gun Turret. Remove
end pin sockets (fig. 226).
packed gun turret container from forward left side of car-
c. Aline Lifting Crane. Position craned aft
go floor, aft of main rotor head and mast unit (fig. FO2).
of helicopter tail. Aline crane lifting hook
229.22 Unload One 2.75 Inch Rocket Launch-
over center of tail rotor gearbox fairing.
ers. Remove one packed 2.75 inch rocket launcher
from top of remaining loaded Hellfire launcher (fig.
FO2).
CAUTION
229.23 Unload One Hellfire Launcher. Remove
packed launcher container from forward right side of
Sling will be tensioned at this point
cargo floor, aft of main rotor head and mast unit (fig.
only enough to remove strap slack.
FO2).
Hoistloading the stowed vertical sta-
229.24 Unload Two Main Rotor Head and Mast
bilizer will cause major structural dam-
Units.
age.