TM 55-1520-238-S
230.7 Install
g. Couple Sling to Crane. Connect crane
Tail
Rotor
lifting hook to air vehicle sling link (lifting
eye). Carefully operate crane winch to re
230.8 Install
Horizontal
move all slack from sling cables.
h. Remove Main Rotor Head and Mast Unit
from Shipping Carrier. Operate crane
winch and carefully lift main rotor head and
mast unit straight up and out of the carrier.
Conduct depreservation of coated sur-
WARNING
faces. Hoist the unit high enough to clear
helicopter upper fuselage.
During this procedure, helicopter must
be on a level surface, with landing gear
CAUTION
in normal static condition (not
kneeled). If helicopter is tilted, main ro-
Mixer supports must be centered
tor head and mast unit may slip and
over their mast base holes, and main
swing, causing possible injury of per-
rotor drive shaft must be properly
sonnel or equipment damage.
alined with main transmission drive
a. Remove Main Transmission Access
splines, to prevent damage to criti-
Panels. Release 12 camloc fasteners at
cal mixer and rotor drive compo-
each panel (L200 and R200).
nents.
When lowering main rotor head and
b. Check Drive Shaft Spring. If not pre-
mast units, carefully maintain cen-
viously removed, lift shipping cover from
tral alinement of drive shaft,
top of main transmission. Check position of
installed drive shaft spring and
main rotor drive shaft spring. Spring must
standpipe, and the drive plate open-
be centered over the transmission drive
ing, to prevent parts damage or mis-
shaft hole (fig. 223).
alinement.
c. Install Air Vehicle Sling on Main Rotor
i. Aline Main Rotor Head and Mast Unit
Head. Couple sling fittings to lifting cle-
Over Mast Base. Center the main rotor
vises on main rotor head, in the shipping
drive shaft over drive shaft spring in main
carrier (fig. 223).
transmission, and rotate the unit to aline
d. Aline Lifting Crane Over Main Rotor
right and forward mixer supports over mat-
Head. Center the crane lifting hook over
ing mast base holes.
shipping carrier. Aline lifting hook over
j. Lower Main Rotor Head and Mast Unit
installed air vehicle sling.
Into Place. Slowly lower the unit, and
install forward mixer support bolt and lock
e. Install Mixer Spreader.
washer while the unit is moving down.
TM 1-1520-238-23.
Carefully aline drive shaft splines within
f. Release Main Rotor Head and Mast Unit
main transmission drive splines, and slide
from Shipping Carrier. Open the four
mast flange holes over projecting mast
corner straps securing main rotor head to
base studs. Handtighten mixer support
the carrier frame (fig. 224). Disconnect
bolt.
mixer clevises from carrier turnbuckles. Re-
k. Install 18 New Preload Indicating (PLI)
move mixer support bolts and static mast
washer sets (D22) and Torque 18 Mast
bolts.
Base Nuts.
TM 1-1520-238-23.
l. Install Right Side Mixer Support Bolt
CAUTION
and Lock Washer. Handtighten bolt.
m. Seat and Torque Forward and Right Side
Mixer Support Bolts to 230 to 280 Foot
Air data sensor and attached deicing
Pounds.
housing are shipped in the carrier with
TM 1-1520-238-23. Use mixer bolt torque
the main rotor head and mast unit. If
adapter (item 51, table 22) with 3/4 drive,
not previously unpacked, the sensor
3inch long extension (item 52, table 22).
and housing unit must be removed
Bend lock washer tabs after final retorqu-
from carrier at this point, to prevent
ing.
damage.