Page Title: Figure 8-34 Attaching guy line to hold second ring staves
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 

TM 5-5430-209-12
f. Installing  Remaining  Intermediate  Staves  in
(4) Gin pole (1, fig. 8-32) is now directly over the
Second Ring.
center of second stave (5, fig. 8-33) position. Keep pull
line (3) outside of the tank. In hoisting a stave, the pull
(1) Install the remaining 34 staves, except the last,
line must form an angle with the pole equal to and
following the procedure in e above.
adjacent to the angle formed by the load lines and pole.
(2) As staves are installed, assemble hook ladder
This will reduce bending of the gin pole and reduce
(3, fig. 8-35) furnished with the storage tank erection
danger to personnel pulling on the pull line should the
outfit.
stave accidentally fall.
(5) Lower hook (4) and attach it to the center bolt
hole in the top chime of second stave (5).
(6) Raise stave (5) and install it following the
procedures in d(6) and (7) above and in paragraph 8-
10c.
(7) Shift the guy line to the new location shown in
1. BOLT HEAD
2. STAVE JOINT CHANNEL
3. HOOK LADDER
ME 5430-209-12/8-35
Figure 8-35. Driving second ring stave bolts into position
ME 5430-209-12/8-34
Figure 8-34 Attaching guy line to hold second ring staves.
8-20