DETERMINING MOBILE MATERIALS
HANDLING EQUIPMENT REQUIREMENTS
FORMULA - V x T 4AT = R
C
EXPLANATION:
V - Volume or size of the operation to be performed.
C - Units of volume carried per trip (pieces, pounds, etc.) by equipment
T - Average expended time to accomplish a complete equipment trip cycle.
AT - Allotted time to do the job.
R - Equipment requirement
Figure 4-105. Formula to be applied in computing MHE requirements.
b. Example use of the formula in figure 4-105 is shown
(1) Storage operations require 48 pallet loads of
in the following situations:
supplies to be relocated a distance of 250 feet. One
round trip takes 5 minutes, and 2 hours is the time
allotted. Two pallets are carried each trip.