Page Title: Table 5-4. Power Distribution Box Troubleshooting Procedure (Cont)
Back | Up | Next

Click here for thousands of PDF manuals

Google


Web
www.tpub.com

Home


   
Information Categories
.... Administration
Advancement
Aerographer
Automotive
Aviation
Construction
Diving
Draftsman
Engineering
Electronics
Food and Cooking
Logistics
Math
Medical
Music
Nuclear Fundamentals
Photography
Religion
   
   

 

TM 32-6110-003-24&P
Table 5-4. Power Distribution box Troubleshooting Procedure - Continued
Step
Test Point
Test Equipment
Procedure
Normal Indication
If Indication is
If Indication is
Normal
Abnormal
+28 V dc for each
If voltage missing at
5 Cont
e.
With multimeter connected to
check.
connector pin J10-G,
ground stud , measure voltage at
replace
circuit
connector pins J10-G, J10-R,
breaker CB14, filter
and J10-L.
FL1, or relay K1.
If voltage missing at
connector pin J10-R,
replace
circuit
breaker CB12 filter
FL3, or relay K1.
If voltage missing at
connector pin J10-L,
replace
circuit
breaker CB13 filter
FL2, or relay K1.
f. Set circuit breakers CB12 through
+28  V  dc  slowly
Proceed with step
If voltage present at
CB14 to off (out) position and turn
bleeding down to 0
6.
J10-L, J10-G or J10-
power supply off. Connect a 600
volts.
R,  replace  related
ohm, 2 W resistor between J10-L
circuit breaker.
and ground to bleed off the in-line
filter discharge. Monitor the dis-
charge with a multimeter. Repeat
the procedure for J10-G and J10-
R. (See figure 5-3.)
5-10