11-30. AIR GOVERNOR TESTING/ADJUSTMENT
This task covers:
a. Testing
c. Follow-On Maintenance
b. Adjustment
INITIAL SETUP
Equipment Conditions
Tools and Special Tools
Air system drained (TM 9-2320-360-10).
Tool Kit, Genl Mech (Item 54, Appendix F)
Lower engine access panel removed
a. Testing
(1) Start engine (TM 9-2320-360-10).
(2) Watch air pressure gage (1). Green and
red needles (2) should move up scale as
pressure builds up.
NOTE
When governor cuts out, released air
from air dryer can be heard.
(3) After several minutes, gage needles (2)
should stop at 120-125 psi (827-862 kPa)
as governor cuts out.
(4) Adjust governor (3) if it does not cut out at
120-125 psi (827-862 kPa).