TM 9-2320-285-24-2
4-3.
TORQUE CONVERTER (CONT)
STEP
LOCATION
ITEM
ACTION
REMARKS
REASSEMBLY (cont)
22
parts affecting end play are
(cont)
installed. Otherwise, do
not
install spacer (2) at this
time
d
Bearing race
Install
Outer lip up
(19)
e
Bearing
Install
Grease first with oil-soluble
assembly (18)
grease
23
Plate (16)
New seal ring (17)
Install
24
Converter
a
Plate (16)
Install
Line up balance marks
pump assem-
b
Plate (15)
Install
bly (14)
Install
25
Cover
a
New bushing
If original was removed. Use
assembly
(12)
bushing installer, as shown.
(3)
After installation, bushing
(12) inside diameter should
BE 0.9990 to 1.0010 inch
TA236042
b
Seal ring
Install
Onto hub, smaller end first
retainer (10)
26
Seal ring
New ring (11)
Install
retainer
(10)
27
Piston (7)
New ring (13)
Install
4-15
|