TM 9-2320-270-20-2
AUXILIARY TRANSMISSION TO TRANSFER CASE PROPELLER SHAFT' - CONTINUED
ACTION
LOCATION
ITEM
REMARKS
Flange yoke (6)
Eight screws (8),
4.
a. Using 15/16-inch socket, handle, and
Iockwashers (9),
to auxiliary
15/16-inch wrench, unscrew and take
transmission (7)
and nuts (10)
out.
b. Get rid of Iockwashers (9).
Transfer case yoke
5.
Splined shaft (12)
a. With the aid of an assistant, and using
with sleeve yoke (13)
(1) and auxiliary
pry bar, rotate up and take out.
transmission flange
b. Tip cross (14) out of yoke (1) and take
and flange yoke (6)
yoke (11)
out.
Dust cap (15), steel
6.
a. Using pipe wrench, unscrew.
washer (16) and
b. Slide off sleeve yoke(13) and onto
cork washer (17)
splined shaft (12).
Splined shaft (12)
7.
Pull off.
Sleeve yoke (13)
with flange yoke (6)
Dust cap (15), steel
8.
Take off.
washer (16), and cork
washer (17)
TA240383
4-565
|