TM 38-260
EXAMPLE 2 LAYAWAY IN PLACE TO LEVEL " " FOR (3) 3000 lb. DRILLS. ASSUMING A LABOR RATE OF
A
20.00/HR, 2000.00 TOTAL TOOLING REPL COST FOR 3 DRILLS, AND 1000 MILES TO TRANSPORT.
3000 + 3000 + 3000 = 9000 lbs. total wt. (3) drills; 9000/4,000 = 2.25 round down 2 machines. Conversion to 3 ton class.
3 TON
LAYAWAY ACTIONS
(4000-8,000 lbs)
MAN HRS
MATERIAL
1. FLUSH
6
65.00
3. CLEAN EXTERIOR
4
18.00
4. DISASSEM-CLEAN-REASSM
42
38.00
5. PRESERVE LEVEL'A'
8
65.00
13. SHROUD
3
21.00
15. RECORDS & OFFICE
4
18.00
16. INCIDENTALS/MISC
4
13.00
71
238.00
71 M/H X 20.00/HR Labor
= 1420.00
Material cost
= 238.00
TRSPN
1.02 X 1000 Mi
= 1020.00
Tooling
.06 X 2000
= 120.00
= 1658.00 X 2 (4 Ton Equiv. Mach)
= 3316.00
ESTIMATED PCH&T FOR (3) 3000 lb. DRILLS
= 4456.00
B-4
|