TM 38-260
SAMPLE PCH&T ESTIMATES
EXAMPLE 1: LAYAWAY OFF SITE FOR A 12,000 lb. MILLING MACHINE. ASSUMING A LABOR RATE OF
38.16/HOUR, 3500.00 TOOLING REPL COST, AND 500 MILES TO TRANSPORT.
6 TON
LAYAWAY ACTIONS
(800-16,000 Ibs)
MAN HRS
MATERIAL
.1.
FLUSH
8
75.00
.2.
DISCONNECT
4
12.00
.3.
CLEAN EXTERIOR
5
28.00
.4.
DISASSEM-CLEAN-REASSEMB
66
60.00
.5.
PRESERVE LEVEL'A'
14
159.00
.6.
PRESERVE LEVEL'C'*
6
60.00
.7.
MOVE TO SKID & BOX AREA
6
53.00
.8.
SKID & BOX (ALUM SKID)
14
49.00
.9.
SKID & BOX (WOOD SKID) *
20
1235.00
10.
MOVE TO LOADING DOCK
4
34.00
11.
LOAD & BRACE (TRUCK)
5
53.00
12.
LOAD & BRACE (RAIL) *
14
117.00
13.
SHROUD (POLYETHYLENE)
6
37.00
14.
MOVE TO STORAGE AREAS-LEVEL
6
47.00
15.
RECORDS & OFFICE
4
18.00
16.
INCIDENTALS/MISC
4
13.00
186 M/H
2050.00
Manhours 186 X 38.16/HR commercial labor rate
= 7097.76
Material cost
= 2050.00
Tooling cost .06 X 3500.00 estimated tool repl
= 210.00
Transportation) 1.02 X 500 miles
= 510.00
Estimated PCH&T Cost for (1) 12,000 lb. Mill
9867.76
*This chart is intended to show all actions to be considered. Some layaway actions may not be required depending on the
disposition of the IPE. Labor rates and material costs will vary based on geographic location. Labor rates used are for
example only. Results of this calculation are estimates.
B-3
|