TM 9-2350-238-20-1
1 If removed, apply adhesive to four new radiator bulkhead seals (1) and four new radiator
bulkhead rubber strips (2) and install.
2 Install two filler opening caps (3).
3 Install two new radiator tube assembly gaskets (4), radiator surge tank metal tube assembly (5),
and radiator pressure equalizing metallic tube (6), and secure with eight new packings with
retainers (7) and eight hexagon head capscrews (8). Torque hexagon head capscrews to 1.2 to
1.5 ft-lb (1.6 to 2.0 N-m).
4 Install two drain cocks (9).
5 Install two radiator base resilient mounts (10) and secure with six machine bolts (11), six new
Iockwashers (12), and six hexagon plain nuts (13). Torque hexagon plain nuts to 17 to 19 ft-lb
(23 to 26 N-m).
2-521
|