TM 9-2320-285-24-2
4-4.
TRANSMISSION (CONT)
b.
Main Shaft and Gear Unit Assembly.
This task covers:
a.
Disassembly
c. Inspection
b.
Cleaning
d. Reassembly
INITIAL SETUP
Tools
No 2 Common Organizational Maintenance
Pin remover and installer spacer
Tool Kit
J-25587-6
Flat tip screwdriver
Pin installer J-25587-11
Twist drill set
Pin installer J-25587-12
Retaining ring pliers
Pin installer J-25587-13
Mechnical puller kit
Pin remover J-25587-16
Safety glasses
Bottom swaging tool holder J-25587-17
Thickness gage
Four 3/4 inch loading pins J-25587-18
Slip joint pliers
Six 1/2 inch loading pins J-25587-22
Arbor press, 10 ton capacity,
Two swaging tools J-25587-23
adjustable bed of 25 inches
Two swaging tools J-25587-27
minimum opening
Four 3/4 inch guide pins J-25587-48
Drill press
Six 1/2 inch guide pins J-25587-50
Lathe
Soft-jawed vise
Materials/Parts
Main and output shaft orifice installer
Cleaning solvent
Item 1, Appendix C
J-24369
Clean cloths
Item 2, Appendix C
Sun gear shaft bushing installer Oil-soluble grease
Item 9, Appendix C
J-24468
Front planetary bushing installer Personnel Required
J-24469
Automotive Repairer MOS 63H
Planetary carrier rebuild tool kit
J-25587-01
Equipment Condition
Removing, installing and swaging
Paragraph Condition Description
fixture J-25587-1
Pin remover and installer adapter
4-4e
Main shaft and gear unit
J-25587-2
assembly removed from trans-
Support block J-25587-3
mission
Support block J-25587-4
STEP
LOCATION
ITEM
ACTION
REMARKS
DISASSEMBLY
1
Main shaft
a
Thrust washer
Remove
and gear
(1)
unit
b
Thrust washer
Remove
assembly
(2)
c
Front sun gear
Remove
Main shaft and gear assembly
(3)
positioned shaft (4) end up
d
Thrust washer
Remove
(5)
4-24
|