TM 55-1520-238-S
d. Main Rotor Drive Plate Cover.
d. Preservation. Thoroughly coat blade
Cover main rotor drive plate cover with bar-
root fitting bolt holes with corrosion preven-
rier material (D1), secure with tape
tive compound (D4). Wrap each blade
(D13).
root area with barrier material (D1). Se-
cure with tape (D13).
e. Connection Closure. Cap or wrap dis-
e. Install Blades in Racks. Install blades in
connected deicing connectors with barrier
blade rack sets (items 1 and 2, table 21)
material (D1) secure with tape (D13).
(fig. NO TAG).
f. Preservation. Apply corrosion preven-
(1) Remove upper and intermediate racks
tive compound (D4) to all exposed sur-
from blade root and blade tip racks.
faces of ADS mast, distributor and stand
pipe.
(2) Install first blade in lower blade root and
lower blade tip racks.
g. Component Wrap. Wrap ADS mast, dis-
tributor, and stand pipe with barrier material
(3) Place intermediate racks on top of
(D1) and cushioning material (D5), se-
blade.
cure with tape (D13).
(4) Place second blade on intermediate
h. Stowage. Stow wrapped cushioned ADS
racks with blade root of second blade
mast, distributor, and stand pipe in catwalk
inset approximately six inches from
area.
first blade root.
i. Install Panel.
Install panel R200.
(5) Install upper racks on blade root and
blade tip racks.
232.4 Install Forward Fuselage Tiedown Fittings.
(6) Repeat steps NO TAG thru NO TAG
for third and forth blades.
NOTE
f. Remove Wedges. Remove droop stop
Landing gear cross tube end studs have
wedges for use on next helicopter to be
nuts at both ends. One cotter pin and nut
prepared.
will be removed from each stud, and stud
will be pulled in direction allowing clear
232.2 Position Drive Train. After removal of main ro-
removal.
tor blades, position the drive train so that the main rotor
pitch housings are positioned 45 to the centerline of the
a. Remove Main Landing Gear Cross Tube
fuselage and the tail rotor blades are ``X ed'' horizontally
End Caps. Remove one cotter pin, nut,
and secured as shown in figure 234. Use rope, D28.
and washer from cross tube left and right
end cap studs. Pull studs (with pinned nuts
232.3 Remove Main Rotor Deice Power Distribu-
in place) from cross tube. Slide caps from
tor, Air Data System (ADS) Mast, and Stand Pipe.
cross tube ends. Retain removed studs,
a. Remove Panel. Remove panel R200.
washers, and nuts. Discard removed cotter
pins (fig. NO TAG).
NOTE
CAUTION
If installed angle of cross tube stud pre-
vents stud removal, helicopter must be
To prevent contamination of main ro-
jacked or lifted and cross tube rotated
tor drive shaft and stand pipe, cover
(TM 1-1520-238-23).
drive plate cover as soon as sensor
housing unit and stand pipe are re-
b. Install Tiedown Fittings. Slide tiedown
moved.
fittings (item 6, table 21) into left and right
ends of each main landing gear cross tube.
b. Component Removal. Remove main
Aline holes in fittings and cross tube, and
rotor deice power distributor, air data sys-
install removed studs, washers, and nuts.
tem mast, and stand pipe (fig. NO TAG and
TM 1-1520-238-23).
c. Stow Removed Cross Tube End
c. Secure Cables. Reinstall (for stowage)
material (D5), secured with tape (D13).
removed wire guides and cable clamps.
Stow wrapped end caps on floor of pilots
Secure cables to deicing housing with twine
station.
(D14).
Change 4
281
|