NOTES.
a. Remove curbs, ramps and deck units and add counterweight if
required.
b. Skid bridge to correct bearing.
c. Position ex. FRB under bridge 3 ft (0.9 m) from new A peg. Bridge
should overhang ex FRB min.1.5 ft (0.5 m).
d. Position CRB next to ex FRB.
e. Add LNCG posts. LNCG, nose roller and install launching nose,
then position LRP 12 ft from A peg.
f. Delaunch bridge until far BSB is 6 ft (1.8 m) from A peg or end of
ETP overhangs CRB by min. 1.5 ft (0.5 m)
g. Reposition LRP against new A peg and then remove ex. FRB.
h. Stop boom/delaunch to remove long or short links, light tackle, anti-
flutter and add launching noses as required, observing minimum 5 ft
(1.5 m) overhang.
i. Disassemble FRB and RRB. Clear site.
* Remove entire launching nose, LNCG, LNCG posts and nose
roller.
( ) Center of gravity.
2-77
|