NOTES:
a. Add LNCG posts, LNCG and nose roller.
b. Stop boom/launch to add long or short links, light tackle and anti-
flutter as required.
c. Check that LR is under LZ given or higher. Remove nose sections
as they pass LRP, observing minimum 5 ft. (1.5 m) overhang. Leave
last three nose sections in place until far bank end of bridge has
been lowered to ground.
d. Boom to 6 ft. (1.8 m) from A peg or ETP overhangs CRB by min.
1.5 ft. (0.5 m).
e. Install ex FRB in front of CRB and then reposition LRP 12 ft. (3.6 m)
from A peg.
f. Launch to required far bank bearing or until end of ETP overhangs
ex FRB bt 1.5 ft (0-.5 m).
g. Reposition counterweight deck units to final position and put bridge
on ground.
* Add given length of launching nose with LRP secured with tie-down
strap.
** Nose completed by adding further LNH's.
[ ] Counterweight.
( ) Center of gravity.
2-66