TABLE 2-24 Building and Boom Table-2E +5 through 2E + 6 Bay
Double Story (Restricted Site)
2E + Bays
5
6
L/Nose
5N1
6N1
5N1
6N1
Boom
2p2
2p6
Remove
4
5
(CG)
(Bp0)
Boom
1p5
2p4
Remove
3
4
(CG)
(Cp1)
(Bp4)
Boom
1p2
1p2
1p2
1p2
Remove
5N1*
6N1*
5N1*
6N1*
(CG)
2
2
3,2
2
Boom
Bp2
Bp2
Bp2
Bp2
Remove
1,E
1,E
1,E
1,E
Complete by:
Note e
Note e
Note e
Note e
NOTES:
a.
Remove curbs, decks and ramps and position FRB under bridge
min 1.5 ft (0.5 m) from the end.
b.
Position center of LR (in LRP) 8 ft (2.4 m) from BSB.
c.
Add LNCG posts, LNCG and nose roller. Add 3 LNH. Reposition
LRP [base 9 in (23 cm) from BSB.]
d.
Add remaining nose sections, observing minimum 5 ft (1.5 m)
overhang.
e.
Desassemble FRB and RRB. Clear site.
*
Remove entire launching nose, LNCG, LNCG posts and nose
roller.
()
Center of gravity.