NOTES:
a.
Add LNCG posts, LNCG and nose roller.
Check that LR is under LZ given or higher Remove nose sections
b.
as they pass LRP, observing minimum 5 ft (1.5 m) overhang.
Leave last three nose sections in place until far bank end of bridge
has been lowered to ground.
Launch until far bank end of bridge is 9 in (23 cm) from LRP, or
c
end of ETP overhangs CRB by 1.5 ft (0.5 m).
d.
Put bridge on ground
*
Add given length launching nose with LRP secured with tie down
strap.
**.
Nose completed by adding 8th LNH or 6 LNH required for 3N2
(double-story nose).
()
Center of gravity
2-19
|