NOTES:
a. Remove curbs, deck units and ramps.
b. Install RB under bridge minimum 1.5 ft (0.5 m) from end. If mini-
mum bearing is being used, position RB under center hole of
BSB.
c. Position center of LR (in LRP) 8 ft (2.4 m) from BSB.
d. Add LNCG posts, LNCG, nose roller and 3 LNH. Reposition LRP
[base 9 in (23 cm) from BSB]. Add LNH 4.
e. Place BSB to side of site near end of bridge.
f. Add launching nose sections as required, observing minimum
5 ft (1.5 m) overhang.
g. Position BP as required to keep bridge off ground.
h. Remove BSB. clear site.
[ ] Counterweight. (Counterweight BSB connected by shootbolts
only).
( ) Center of gravity,
2-13
|